5.5.2016
Precast Piling Technologies mastered an installation work at the FedEx distribution center, Saint Petersburg, FL, United States.
Precast Piling Technologies, Inc. from Tampa used two of their Junttan rigs for installation. Installation rate was 35 to 40 piles a day driving all day with one rig and ½ day with the other. The work went smoothly with an excellent cooperation of all parties working on the site.
The key measurements for this site are: an approx. 230,000sf building, with approx. 1700 piles 72’ long (22 meters) and 12” pre-stressed concrete piles, which are spliced with the Leimet ABB Plus pile joint.
For more details, please contact Olli Inkinen: +358 40 722 3967 or Dave Harper: + 1(757) 677-6466.

2026 marks an extraordinary chapter in Junttan’s history – our 50th Anniversary Year! Over the decades, our journey has been shaped...
29.10.2025
Only four months to go! We’re excited to invite you to CONEXPO-CON/AGG 2026, North America’s largest construction trade show, taking...
27.10.2025
Junttan’s fully battery-powered pile driving rig, the PMx2e, has been at the heart of another milestone in sustainable foundation construction...
23.10.2025
We’re delighted to welcome VDR Marine Equipment as Junttan’s new Authorized Service Partner and Spare Parts Provider in the Middle...
6.10.2025