Aarsleff Ground Engineering UK, in Avonmouth, Great Britain, installed a total of 10,000no driven precast concrete piles for Lidl UK ‘s new 600,000 sq ft (55 742 sq m) distribution warehouse.
They used two Junttan PMx22 rigs, a Junttan PM20 HLC, two Junttan PMx20’s and a Banut 800 with Junttan hydraulic hammer. Each rig was driving between 25 and 40no piles per shift, circa 1,000no per week.
Precast piles (250 mm2) was driven between 14 and 20m-deep across the site over a 12 weeks period. The piles, which were cast in standard square sections from 200mm to 400mm and from 4m in length, increasing in 1m increments to standard lengths of up to 14m. A further 300 no 273mm diameter by 18-23m deep tubular steel piles were also driven, to complement the overall foundation works, including the test piles.
Due to the poor ground conditions made up of soft clay, there was no scope for traditional foundations. The sheer scale of the Lidl building and its roof stanchions obviously having a larger load, consequently required more foundation support from Aarsleff. The level of depth that they drove was simply based on site investigation and design. Ground like soft clay with poor bearing capacity, the simplest solution was to drive down to rest on bedrock layer.
We are excited to announce that Adam Baker joined the Junttan team as VP Sales & Operations at Junttan UK...
12.2.2025
Bauma 2025 is just two months away! The 34th edition of the world’s leading trade fair for construction machinery is...
5.2.2025
KUOPIO, FINLAND, 30th JANUARY 2025 Junttan, a global leader in pile driving equipment manufacturing, announces the launch of the new...
20.1.2025
We’re excited to share that Junttan has been actively collaborating with key industry players, including Liebherr, Bauer, and ABI, as...
15.11.2024